[Foundation Evaluations]
- Review the foundation plans and specifications as they relate to the existing soil conditions
- Provide foundation preparation recommendations for soils not meeting minimum design requirements
- Provide cost effective engineering solutions for existing foundations undergoing excessive settlements
Construction Testing:
- Perform hand auger with dynamic cone penetrometer testing to verify existing soil conditions within foundation excavations
- Verify foundation excavation dimensions are in accordance with the design drawings
- Inspect rebar to verify the appropriate size and spacing based on the specifications noted on the drawings
- Evaluating the soil support conditions around existing foundations that have undergone excessive settlement
- Monitor pile installation
|
|